A conference run sheet is one timed document that says what happens, when, where, and who owns it. The version below is built for a Fiji one-day conference with a gala dinner, and includes the two columns most run sheets leave out: the crew call and the supplier arrival window. Copy it and change the times.

Every time in this template is illustrative. The structure is the point.

What must a conference run sheet contain?

Six columns, and no more than six, or nobody reads it on the day.

  1. Time — in 5- or 15-minute increments, never "morning".
  2. Item — one action per line.
  3. Owner — a named person, not a company.
  4. Location — the specific room or door, not the property.
  5. Crew call — who must already be in position, and since when.
  6. Notes — the one thing that goes wrong if this line slips.

A seventh column for radio channel is worth adding once you are above 200 delegates.

The conference day run sheet

TimeItemOwnerLocationCrew callNotes
05:30Venue access, ballroom unlockedVenue duty managerBallroomAV crew on site 05:30Confirm access time in the contract, not by email
05:30Final AV check, mics, comms testAV leadBallroomFull AV crewTest every lapel, not a sample
06:30Registration desk build, signage outRegistration leadFoyer2 staffPower and wifi at the desk confirmed
07:00Breakfast opens for crewCatering managerStaff area—Crew eat before delegates arrive, not with them
07:15Coach 1 departs airport hotelTransport coordinatorHotel porte-cochèreMarshal in position 07:00Manifest printed, not on a phone
07:40Coach 1 arrives, marshalling beginsTransport coordinatorSet-down point2 marshalsOne marshal per door, always
07:45Registration opensRegistration leadFoyer4 staffQueue flow rehearsed yesterday
08:00Doors open, holding music, walk-in loopAV leadBallroom—Lights to 70%
08:25Speaker briefing, mics fittedStage managerGreen roomStage manager + AVBrief every speaker, including the one who says they don't need it
08:30Welcome and openingMCBallroomFull crewCue sheet in the MC's hand on paper
08:40Traditional welcome / sevusevuCultural liaisonBallroomPerformers on site 08:00Protocol confirmed with the performing group in advance
09:00KeynoteStage managerBallroom—Countdown clock visible to the speaker only
10:00Morning breakCatering managerFoyerCatering 09:45Stations open before the room empties
10:30Breakouts beginSession leadsRooms 1–31 tech per roomSignage and a human at every door
12:30LunchCatering managerTerraceCatering 12:00Wet-weather call made at 10:00, not 12:00
13:30Afternoon plenaryStage managerBallroom—Lighting state reset from breakouts
15:30Close, delegate departuresMCBallroomMarshals 15:15Coaches staged, engines off
15:45Ballroom turnaround to gala setProduction leadBallroomFull crew + venue staffThis is the tightest window of the day
17:30Gala room ready, lighting checkProduction leadBallroomAV + venueWalk the room with the client
18:30Pre-dinner drinksCatering managerLawnBar staff 18:00Second wet-weather call at 16:30
19:15Guests seatedMCBallroomFull crewSeating plan at every door
19:30Entrée service, welcome speechCatering + MCBallroom—Speeches between courses, never during
21:00EntertainmentStage managerBallroomPerformers 20:00Sound check done before guests seated
23:00Carriages, first coaches departTransport coordinatorSet-down pointMarshals 22:30Last coach 00:30, published to delegates
23:30Bump-out beginsProduction leadBallroomFull crewConfirm bump-out window in the contract

What are the supplier arrival windows?

The run sheet above assumes these are already agreed in writing. Agreeing them late is how a Fiji event goes wrong.

SupplierArrival windowWhy it matters
AV and staging freight48 hours before, minimumCustoms clearance and inter-island transport sit upstream of this
AV crewDay before, for bump-inSame-day bump-in on a conference of any size is not a plan
Marquee and hireDay beforeGround conditions can change overnight
Catering45 minutes before each serviceStations open before the room empties, not after
Cultural performers30 minutes before, briefedProtocol and payment agreed in advance, always
Coaches15 minutes before scheduled departure, engines offA coach that arrives on time has already failed
PhotographerWith the first delegateThe registration queue is the shot nobody gets

Equipment coming into the country has its own lead time — see bringing event equipment into Fiji: customs and carnets and staging, rigging and set build in Fiji.

The four lines Fiji run sheets usually miss

The wet-weather call, with a named decider and a time. Not "if it rains". Write the time the call is made, who makes it, and what happens on each answer. Our guide to wet-weather contingency planning for outdoor programmes has the decision tree.

Coach marshalling, not coach arrival. A coach arriving is not delegates boarding. One marshal per door, a printed manifest, and a named person who counts heads before the door closes. Building a transport plan for a Fiji conference covers the mechanics, and operators such as Tourist Transport Fiji and Pacific Transport Limited have the fleet.

The cultural welcome as a booking, not a backdrop. Performers and chiefs are contracted, briefed, credited and paid like any other supplier. Fijian warriors, meke and choirs: booking performers respectfully sets out how.

Power. Ask the venue, in writing, what happens when the mains drop and how long the changeover takes. Power reliability and generator backup explains what to ask for.

How to distribute it

Print it. Three versions: the full sheet for the core team, a one-page crew call sheet for suppliers, and a delegate-facing programme with no crew detail on it at all. Then put a named person on a radio at every location on the sheet.

If your group is arriving into Nadi and staying at an airport-area hotel such as the Crowne Plaza Fiji Nadi Bay Resort & Spa or on Denarau at the Sheraton Fiji Golf & Beach Resort, start with airport meet and greet for conference groups and the venue's own published capacities on the capacity chart. An inbound operator such as Rosie Holidays can own the ground portion of this sheet end to end. The full planning sequence is in the business events in Fiji guide.